Repair of 170 MVA transformer, Koman HPP
Value10.936.837 Lek
FundingWith borrowed funds
Starting Date28.08.2014
End Date27.11.2011
Scope

To improve the power supply infrastructure at the headquarters premisses of KESH Tirana, by enabling the power supply with 2 lines from 20/0,4 kV, 10/0,4 kV cabins, and installation of a 150 kVA motor-generator, which shall be on standby to supply energy for the building in case of lack of energy supply from the aforementioned lines. These 3 power sources will be automatically controlled through the supply, installation of a change-over with a priority supply from the 20/0,4 kV line. In addition, works and installations will be performed to improve the telecommunication system of the building, the air conditioning, ventilation, fire detection and extinguishing in the server room. F.V. LV Cabin 300x190x230 construction with sandwich panels for outdoor.

Main activities

• Power supply of KESH head quarters, LV 0,4 kV network, Underground cable line AL 4x240mm2 from 20/0,4 kV
“Vasil Shanto 1” Cabin
• Cable line and LV Cabin
• LV 0,6/1kV Cable (LV output of KESH)
• Cabin
• Construction Works
• Construction of BOX Type Cabin, Low Voltage 0,4kV and territory rehabilitation behind

KESH building:

• Construction of foundation pad and LV 0,4kV Cabin
• Works for territory rehabilitation behind KESH building
• Works for the improvement of rooms no. 107, 108. Telephone, internet network for KESH
• Works for the improvement of the room no. 107.
• Works for the improvement of the room no. 108.
• Improvement of telephone, internet networks and equipment, work places KESH
• Supply and installation of the generator for KESH Building
• Air conditioning, ventilation, fire detection and extinguishing system in the server room and cabin
• Supply and installation of batteries (128 pcs) for the main inverter.
• Inst. automatic with three sources (2 LV lines+generator)
• Inst. of LV panel, 10 outlets; 2 measurements; 170x190x45 fully equipped

Expectations

The works were performed within the term established under the contract and the object is achieved according to the project. The implementation of this contract has made possible the power supply for the headquarters of KESH Tirana, uninterruptedly from three independent sources. Specifically, in case of lack of power supply, the building will be supplied with power from 2 cabins, 20/0,4kV and 10/0,4kV. If there is no electric power coming from these lines, the 150kVA Diesel-generator starts automatically, and it has been tested under load. The distribution of the loads in all the relevant floors, uniformly in 3 phases, has been improved. Power supply was provided for the second floor, where the inverter is located and of the server room. Improvement of telephone, internet networks and equipment, work places KESH.